Fluvanna County Public Schools

...charting a course for innovation and excellence to create world-class learners.

School Construction

Design Plans for the New High School are available in the School  Board Office for public review.

Text Box: Project Schedule 
(as presented to the School Board on 1/11/2009)

Schematic Design		April 2007-February 21, 2008
Design Development		February 22, 2008 - May 30, 2008
Construction Documents	June 2, 2008 - January 23, 2009
	
	Submit Construction Documents for Building Permit

Advertise for Bids		January 25, 2009
Bidding				January 2009/February 2009
Receive Bids			February 25, 2009
School Board Bid Review	March 11, 2009
Contract Award			March 2009
Construction			April 2009 - November 2011

High School Construction Update– 10/14/2009

 

Central Auditorium Renovation Slide Show

 

Construction of the New High School Slide Show– 10/14/2009

 

 

Groundbreaking for the New High School

On Tuesday, April 14, Fluvanna County Public Schools held a groundbreaking ceremony for the new high school to be located at Pleasant Grove.

 

BCWH Architects designed the high school, and Nielsen Builders, Inc. is the school’s contractor.

 

Slide Show of Groundbreaking (wmp)

 

Architect’s Presentation at the Parent Forum on April 30, 2009 (PDF)